In February 2015, our community voted to support the school district's bond measure to build a new high school. This project includes a new stadium, Veterans Memorial, expanded classroom space, updated science labs, new library and commons, and a renovated gym and auditorium. This will be a space our community can be proud of!
KEY TIMELINE EVENTS
-
May 2016 - Construction begins on Rice Field Athletic Complex/Veterans Memorial Plaza
-
May 2016 - Completion of design development phase for high school
-
October 2016 - Opening of Rice Field Athletic Complex/Dedication of Veterans Memorial Plaza
-
April 2017 - Construction begins on Anacortes High School
-
Summer 2018 - Start demolition and reconstruction/ modernization of west building
-
September 2018 - Opening of new classroom building; construction of new Cap Sante High School; ongoing renovation of Brodniak Hall, gymnasium, music, drama, and Career and Technical Education (CTE) wing
-
September 28, 2018 - AHS Community Open House & Ribbon Cutting Ceremony - 4-5:30 p.m. at AHS Commons
-
February 2020 - Completion of Cap Sante High School, Brodniak auditorium, gymnasium, music, drama, and CTE wing
RESOURCES
Project Update Email - 6/18/2020
Veterans Memorial Committee
Rice Field Committee
Meeting Minutes, Presentations, and Feedback
Fall 2016 Project Brochure
Fall 2017 Project Brochure
If you have questions, please contact the following:
Project specific questions:
Marc Estvold, Project Manager
(360) 770-3994
[email protected]
or
Dr. Justin Irish, ASD Superintendent
(360) 503-1211
[email protected]